Seyed Mousavi announced: checking
the submarine pipelines of Iranian Oil Terminal Company will be done both
internal and external.
He added: for this purpose, a chain
of multiple projects is defined and the critical points of submarine pipelines
have been identified.
Mousavi stating that the mentioned
project is started due to broken pipes by water pressure, said: fixing these
breaks on the outer surface of the tube is going in review.
He specified: one of the local
companies assumes the responsibility of checking the Iranian Oil Terminals
submarine pipelines with a length of 50 km.
Iranian Oil Terminals Company
director referring to this company's activities in the field of maintenance, said:
these activities are more extensive than in previous years.
He added: repair and reconstruction
operations required for this company is ongoing as planned.